Why transit suddenly costs so much.

Reece Martin · 31 Aug 2026

Read the piece on thetransitbrief.net ↗

3 korrents from this piece ↓

Reece Martin did not write this page.

Every claim below was made in this piece, quoted word for word and numbered in the order the piece makes them, so you can read it there rather than take our word for it. The sentence above each quote is our reading of the claim, not their wording. Each quote was checked against a stored copy of the page at build time; where the two differ, the quote is the fact.

  1. Transit projects - from subways to bus rapid transit - in Canada, and in the English-speaking world writ large, cost far more than projects in many other developed and developing countries, even when adjusting for inflation and differences in the relative value of currencies and inputs.
  2. the problem leading to 5 or 10 times more expensive infrastructure in Toronto or New York is not generally that any one thing is being done ten times worse, but that factors are multiplicative - they compound.
  3. This is reflected by the fact that soft costs - that is, not heavy construction, but planning and engineering - now sometimes cost as much as the entire project might in a place like Italy or Chile.